Intro to Business › Section J · Operations management › Topic J.4
Resource planning, inventory, and production control
A plan to build 10,000 bicycles is worthless if the wheels arrive late, the paint runs out or two teams need the same machine on the same day. Resource planning makes sure the right inputs are in place, and production control makes sure the work happens in the right order and on time.
Planning the inputs
Resource planning starts with a forecast of how many finished products will be needed and when. From the forecast, planners work out which raw materials, parts and components each product requires, using a bill of materials: a list of every item, and the quantity of each, needed to make one unit. A bicycle's bill lists two wheels, one frame, one chain and so on, and each wheel has its own bill of spokes, rims and hubs. Purchasing, also called procurement, then buys the inputs. Materials and bought-in parts are often a large share of total production cost, so resource planning has a direct effect on profit.
Make or buy
For each component the firm faces a make-or-buy decision: produce it in-house or buy it from a supplier. Buying, or outsourcing, usually wins for standard items such as screws and fasteners, and for parts used in small quantities, because specialist suppliers make them more cheaply. Making in-house can win when a component is central to the product's advantage, when its design must be kept secret, or when reliable suppliers cannot be found. A late or faulty part can halt a whole production line, so buying makes strong supplier relationships essential. Section L's topic Supply chain management covers how firms build and manage those relationships across the whole chain.
Why inventory is a balancing act
Inventory is the stock of goods a firm holds: raw materials, work in progress and finished goods. Holding inventory lets a firm meet demand, protects it against supply delays and can capture discounts for bulk orders. But inventory costs money. Holding costs include storage, insurance, spoilage, obsolescence and the opportunity cost of cash tied up in stock. Ordering costs, such as processing orders, delivery charges and receiving goods, are paid each time an order is placed. Large, infrequent orders cut ordering costs but raise holding costs; small, frequent orders do the reverse. Most firms keep a perpetual inventory, a continuously updated computer record of stock levels, orders, receipts and sales.
The economic order quantity
The economic order quantity (EOQ) is the order size that minimises the total of annual ordering and holding costs. With annual demand \(D\), cost per order \(S\) and annual holding cost per unit \(H\):
At the EOQ, annual ordering cost, \(\frac{D}{Q}S\), equals annual holding cost, \(\frac{Q}{2}H\), where \(\frac{Q}{2}\) is the average stock held. The model assumes steady, known demand and a fixed cost per order, so it is a starting point. A related decision is when to order. The reorder point is the stock level that triggers a new order:
where \(d\) is daily demand and \(L\) the lead time in days.
Worked example: ordering bicycle tyres
A bicycle maker uses 12,000 tyres a year. Each order costs 60 dollars to place and receive, and holding one tyre for a year costs 4 dollars. 1. EOQ: \(\sqrt{2 \times 12{,}000 \times 60 \div 4} = \sqrt{360{,}000} = 600\) tyres. 2. Orders per year: \(12{,}000 \div 600 = 20\). 3. Ordering cost: \(20 \times 60 = 1{,}200\) dollars. 4. Holding cost: \(600 \div 2 \times 4 = 1{,}200\) dollars, equal to ordering cost, as the model predicts at the optimum. 5. Reorder point: the plant works 300 days, so daily use is 40 tyres; with a 5-day lead time and 60 tyres of safety stock, \(40 \times 5 + 60 = 260\). Order 600 tyres whenever stock falls to 260.
MRP, MRPII and ERP
Materials requirement planning (MRP) is a computer system that takes the production schedule, explodes it through the bills of materials, subtracts stock on hand and works out exactly which items to order and when, so that each arrives just before it is needed. Manufacturing resource planning (MRPII) extends this to capacity, labour, finance and marketing, so a change in the sales plan flows through to production, purchasing and cash forecasts. Enterprise resource planning (ERP) goes further, linking every department in one shared database and connecting it to suppliers and customers. Section M's topic Management information systems describes how such systems are built and used.
Routing and scheduling
Production control coordinates materials, equipment and people so that work runs as planned and errors are corrected. Its first step is routing: setting the sequence of operations and machines a product or service passes through. Value-stream mapping draws the whole flow of materials and information from supplier to customer, which exposes waiting, rework and bottlenecks. Scheduling then sets when each step happens and how long it should take. The simplest tool is the Gantt chart, devised by the engineer Henry Gantt in the 1910s: a bar chart with tasks down the side and time across the top, showing scheduled against actual progress. Gantt charts are easy to read but do not show clearly which tasks depend on which.
Critical path method and PERT
For complex projects, managers use network methods developed in the late 1950s: the critical path method (CPM), from work by DuPont and Remington Rand, plus PERT, the program evaluation and review technique, from the US Navy's Polaris missile programme. Both list every activity, its duration and which activities must finish first, and draw the links as a network. The longest path through the network is the critical path. Its length is the shortest possible project time, and any delay on it delays the whole project. Activities off the critical path have slack, time they can slip without delaying completion. PERT uses three time estimates for each activity, optimistic \(a\), most likely \(m\) and pessimistic \(b\):
Worked example: launching a product
Activities, in days: A design (4); B order parts (6, after A); C build test rig (5, after A); D assemble prototype (3, after B and C); E test (2, after D); F write manual (4, after A); G ship (1, after E and F). 1. Path A-B-D-E-G: \(4 + 6 + 3 + 2 + 1 = 16\). 2. Path A-C-D-E-G: \(4 + 5 + 3 + 2 + 1 = 15\). 3. Path A-F-G: \(4 + 4 + 1 = 9\). 4. Critical path: A-B-D-E-G, 16 days. 5. Slack: C can slip 1 day, since its path is 1 day shorter; F can slip \(16 - 9 = 7\) days. 6. Check: speeding up F saves nothing, but a 2-day delay in ordering parts makes the launch take 18 days.
Common mistakes to avoid
First, leaving out the 2 or the square root in the EOQ formula. Second, using total stock instead of average stock, \(\frac{Q}{2}\), when computing holding cost. Third, forgetting safety stock in the reorder point. Fourth, calling the critical path the shortest path; it is the longest, and its length is the shortest possible project time. Fifth, speeding up an activity with slack and expecting the project to finish sooner. Sixth, averaging PERT's three estimates equally instead of weighting the most likely time by 4. Seventh, mixing up MRP, which plans materials, with ERP, which links the whole enterprise.
Key takeaways
Resource planning turns a forecast into a bill of materials and purchases, with make-or-buy decisions for each part. Inventory balances holding costs against ordering costs; EOQ = √(2DS/H), and the reorder point = daily demand × lead time + safety stock. MRP plans materials, MRPII adds other resources and ERP links the whole firm. Production control covers routing and scheduling. Gantt charts show progress; CPM and PERT find the critical path, the longest path, and PERT's expected time is (a + 4m + b) ÷ 6.
Flashcards
Flashcard
List of every item, and its quantity, needed to make one unit
Test your understanding
Question 1 of 5
A shop sells 8,000 units a year. Each order costs 25 dollars, and holding one unit for a year costs 10 dollars. What is the economic order quantity?
Question 2 of 5
A café uses 30 litres of milk a day, its supplier takes 2 days to deliver and it keeps 20 litres of safety stock. What is its reorder point?
Question 3 of 5
A project has three paths through its network, taking 12, 15 and 9 days. Which statement is correct?
Question 4 of 5
For one activity, PERT estimates are optimistic 2 days, most likely 4 days and pessimistic 12 days. What is the expected time?
Question 5 of 5
In a project, writing the manual has 7 days of slack. What happens if the manager adds staff so the manual is finished 3 days early?