Location decisions

Once a factory, warehouse or service centre is built, moving it is slow and expensive, so the choice of site locks in costs for decades. This topic sets out the factors firms weigh, two simple tools for comparing sites, and the layouts used inside the building once the site is chosen.

Why location matters

A facility's location affects what it costs to obtain materials and labour, what it costs to ship finished goods, and how easily customers can reach it. Those costs feed into prices and into the firm's ability to compete. Mistakes are hard to correct: relocating a plant means new buildings, lost output during the move and often the loss of trained staff. Firms therefore compare sites carefully before committing. The main groups of factors are the availability of inputs, labour, access to markets, the local manufacturing environment, incentives offered by governments, and, for many firms, the choice between a domestic and a foreign site.

Inputs and labour

Firms whose raw materials are heavy, bulky or perishable, or lose much of their weight in processing, often locate near their sources: sawmills near forests, ore processors near mines, food processors near farms. Firms whose finished products are bulkier or more fragile than their inputs, such as bottlers and bakers, often locate near customers instead. Labour is often the decisive input. Firms compare wage levels, the size and skills of the local workforce, productivity, and how labour relations are organised, including the role of unions. A low wage is no bargain if workers lack the skills the process needs, so many firms weigh labour cost per unit of output rather than the wage alone.

Markets, clusters and incentives

Some firms must be close to customers. Retailers, restaurants, hospitals and banks compete partly on convenience, and a nearby warehouse can deliver faster and more cheaply. The location of competitors matters too, and a chain with several sites must spread them to cover its market. Industrial clusters, places where many firms in one industry already operate, offer pools of experienced workers, specialised suppliers and transport links, which is why new plants often join existing clusters. Governments compete for investment with incentives: tax breaks on income, property or payroll, grants, training support, help with roads and utilities, or faster planning and permit decisions.

Going abroad

Foreign locations can offer lower labour costs, access to materials, fewer or different regulations, and closeness to growing markets. Locating inside a market can also avoid tariffs and long shipping times. This works in both directions: German, Japanese and Korean carmakers have built plants in the United States, such as the BMW plant in Spartanburg, South Carolina, which began production in 1994, to be near American buyers. Foreign sites also bring risks: political change, exchange-rate swings, weaker protection of intellectual property, long supply lines and concerns about labour and environmental standards. Section C's topic Ways to enter the global marketplace covers the wider choices firms face abroad.

The factor-rating method

Many location factors cannot be priced exactly, so firms often use a factor-rating method. First list the factors that matter. Give each a weight reflecting its importance, with the weights summing to 1. Score each site on each factor, say from 1 to 10. Multiply each score by its weight and add the results:

\text{Site score} = \sum (\text{weight} \times \text{score})

The site with the highest weighted score is preferred. The method makes judgements explicit and lets managers test how the answer changes if a weight changes. But the result depends on the weights and scores chosen, so it should support a decision rather than replace one.

Worked example: two sites by factor rating

A firm weighs four factors: labour cost and skills 0.4, transport links 0.3, incentives 0.2 and quality of life 0.1. Site X scores 7, 8, 5 and 6; site Y scores 9, 5, 8 and 7. 1. Site X: \(0.4(7) + 0.3(8) + 0.2(5) + 0.1(6)\) \(= 2.8 + 2.4 + 1.0 + 0.6 = 6.8\). 2. Site Y: \(0.4(9) + 0.3(5) + 0.2(8) + 0.1(7)\) \(= 3.6 + 1.5 + 1.6 + 0.7 = 7.4\). 3. Site Y wins, mainly on the heavily weighted labour factor, despite weaker transport links. 4. Sensitivity check: if transport mattered most, the result could flip, so the weights deserve as much debate as the scores. 5. Check: weights sum to \(0.4 + 0.3 + 0.2 + 0.1 = 1\).

Locational break-even analysis

When costs can be estimated, sites can be compared directly. Each site has annual fixed costs \(F\), such as rent, local taxes and equipment, and a variable cost per unit \(V\), such as labour, energy and shipping. Total cost at volume \(Q\) is

TC = F + VQ

A site with low fixed costs but high variable costs is cheapest at low volumes; a site with high fixed costs but low variable costs is cheapest at high volumes. Setting two sites' total costs equal gives the crossover volume, where the cheapest choice changes; Accounting calls the same idea an indifference point. It is the same algebra as the Accounting course's topic The break-even point, applied to comparing costs rather than revenue and cost.

Worked example: three sites by cost

Site A has fixed costs of 300,000 dollars a year and variable costs of 40 dollars per unit; site B, 500,000 and 30; site C, 800,000 and 25. Expected volume is 45,000 units. 1. Crossover A and B: \(300{,}000 + 40Q = 500{,}000 + 30Q\), so \(Q = 20{,}000\). 2. Crossover B and C: \(500{,}000 + 30Q = 800{,}000 + 25Q\), so \(Q = 60{,}000\). 3. So A is cheapest below 20,000 units, B between 20,000 and 60,000, and C above 60,000. 4. At 45,000 units: A costs 2,100,000 dollars, B 1,850,000 and C 1,925,000. 5. Choose B. 6. Check: B is cheapest at 45,000, which lies inside its range from step 3.

Laying out the facility

After choosing the site, managers design the layout. A process layout groups similar machines or tasks together, such as all welding in one area, and suits firms making small quantities of many products; hospitals use it too, with separate radiology and surgery departments. A product layout arranges stations in a line in the order the product needs them, and suits high-volume flow production, such as car assembly. A fixed-position layout keeps the product in one place while workers and equipment come to it, as with ships, aircraft and buildings. Cellular manufacturing groups the machines needed for a family of similar parts into a compact cell staffed by cross-trained workers, who see each order through from start to finish.

Common mistakes to avoid

First, choosing a site on wages alone; labour cost per unit of output also depends on skills and productivity. Second, forgetting that location is hard to reverse, so short-term incentives should not outweigh long-term costs. Third, using factor-rating weights that do not sum to 1, or treating the result as objective when it rests on judgement. Fourth, choosing the site with the lowest fixed costs without checking expected volume; at high volume, low variable costs win. Fifth, solving a crossover and then not checking which site is cheaper on each side of it. Sixth, mixing up process layouts, grouped by task, with product layouts, arranged in sequence.

Key takeaways

Location decisions are costly to reverse and weigh inputs, labour, markets, clusters, incentives and foreign options. The factor-rating method scores sites as the sum of weight × score. Locational break-even analysis compares total cost, F + VQ, and finds crossover volumes where the cheapest site changes. Layouts are process (grouped by task), product (in sequence), fixed-position (product stays put) or cellular (a self-contained cell for a family of parts).

Flashcards

Flashcard

Location decision

Choosing where to put a facility; costly and slow to reverse

Locks in costs for years.

Test your understanding

Question 1 of 5

Site P has fixed costs of 200,000 dollars a year and variable costs of 12 dollars per unit. Site Q has fixed costs of 350,000 dollars and variable costs of 7 dollars per unit. At what annual volume do their total costs cross?

Question 2 of 5

Using the sites in the previous question, which is cheaper at 40,000 units a year?

Question 3 of 5

A firm weights labour 0.5, transport 0.3 and incentives 0.2. A site scores 6, 9 and 5 on these factors. What is its weighted score?

Question 4 of 5

A shipyard builds large vessels that cannot be moved until they are finished. Which layout fits best?

Question 5 of 5

Why might a firm choose a site with higher wages over one with lower wages?