Accounting › Section S · Activity-based, variable, and absorption costing › Topic S.2
Activity-based product costs
Activity-based costing (ABC) replaces one overhead rate with several, one for each major activity the factory performs. Products then carry overhead in proportion to the activities they actually consume, which often changes the picture of which products make money.
Why one rate can mislead
A single volume-based rate, as in Traditional overhead allocation and cost drivers, assumes every overhead cost rises with labour or machine hours. Many do not. A machine setup costs the same whether the batch that follows has 50 units or 5,000; an engineering change costs the same however many units it affects. A low-volume product made in many small batches uses a large share of setups and engineering time but few labour hours, so a volume-based rate charges it too little and charges high-volume products too much. ABC was developed to fix this by assigning overhead through the activities that cause it.
Activities, cost pools and drivers
An activity is a task that consumes resources: setting up machines, inspecting output, purchasing materials, processing customer orders. An activity cost pool collects all the overhead an activity uses, such as the setup crew's wages, their tools and the materials scrapped during trial runs. Each pool gets an activity cost driver, the measure that best explains its cost: number of setups, inspection hours, purchase orders, engineering change orders or machine hours. The activity rate is the pool's estimated cost divided by the estimated total quantity of its driver.
The cost hierarchy
ABC sorts activities by the level at which their cost is incurred. Unit-level activities happen for every unit, such as machine running time and power. Batch-level activities happen once per batch, whatever its size, such as setups, material moves and first-item inspection. Product-level activities support a product line as a whole, such as design, engineering changes and parts records. Facility-level activities sustain the whole plant, such as the plant manager's salary, building insurance and security. Only unit-level costs truly vary with volume, which is why volume-based rates misallocate the others.
The five steps
Building an ABC system follows five steps. 1. Identify the main activities that consume overhead. 2. Assign the estimated overhead to an activity cost pool for each. 3. Choose a cost driver for each pool and estimate its total quantity for the year. 4. Compute an activity rate for each pool:
5. Assign overhead to each product by multiplying each rate by the product's driver quantity, add the pools, and divide by units to get overhead per unit. The first three steps attach costs to activities; the last two attach activities to products.
Worked example: Halvorsen's activity rates
Halvorsen Audio's $1,500,000 of overhead, previously spread at $30 per labour hour, is analysed into five pools. 1. Machine setups, $300,000 over 100 setups: $3,000 per setup. 2. Quality inspection, $200,000 over 2,500 inspection hours: $80 per hour. 3. Machining, $600,000 over 40,000 machine hours: $15 per machine hour. 4. Product engineering, $250,000 over 50 engineering change orders: $5,000 per order. 5. Facility support, $150,000 over 50,000 labour hours: $3 per labour hour. The five pools total $1,500,000, the same overhead as before; only the way it is shared will change.
Worked example: assigning the pools
Cove (40,000 units) uses 40 setups, 1,000 inspection hours, 30,000 machine hours, 10 change orders and 40,000 labour hours; Summit (5,000 units) uses 60, 1,500, 10,000, 40 and 10,000. In thousands of dollars: 1. Cove: \(120 + 80 + 450 + 50 + 120 = 820\). 2. Summit: \(180 + 120 + 150 + 200 + 30 = 680\). 3. Check: the two total $1,500,000. 4. Per unit: Cove $20.50, Summit $136. 5. Full cost: Cove \(30 + 24 + 20.50 = 74.50\); Summit \(95 + 48 + 136 = 279\). At a $260 price, each Summit loses $19.
Reading the result
Under one plantwide rate the Summit looked like a $57-a-unit winner; under ABC it loses money on every sale. The cause is clear from the pools: with an eighth of the Cove's volume, the Summit uses 60% of the setups, 60% of the inspection hours and 80% of the engineering changes. Managers now have choices to analyse: raise the price, redesign the product to need fewer changes, run larger batches to cut setups, or keep it for strategic reasons. ABC does not make the decision; it supplies a more realistic cost to decide with.
Facility-level costs
Facility-level costs have no activity driver that varies with products: the building is insured whether one product is made or ten. Halvorsen spread its facility pool by labour hours so that unit costs include all overhead, but that share is an arbitrary allocation. Many ABC systems leave facility costs out of product costs for decision-making and treat them as a cost of keeping the plant open. Whichever choice is made, managers should know which part of a unit cost reflects real consumption and which part is a spread of shared cost.
ABC in service organisations
Service firms have little direct material, so overhead is most of their cost and ABC can be especially revealing. A courier might find that collecting from a customer costs $4 per stop, sorting $0.50 per parcel and billing $15 per invoice. A client sending 500 parcels a month on one invoice from one stop a day costs far less to serve per parcel than one sending 20 parcels on 20 invoices from 20 stops. Hospitals, banks and logistics firms use the same thinking to price services and to find customers who cost more to serve than they pay.
Common mistakes to avoid
First, dividing a pool by the number of units instead of by its driver quantity. Second, using a product's share of units to split a batch-level pool: a product's share of setups, not units, decides its setup cost. Third, forgetting to divide a product's total overhead by its own units to get a per-unit figure. Fourth, assuming ABC changes total overhead; it changes only how overhead is shared. Fifth, treating an allocated facility cost as if it would disappear if the product were dropped.
Key takeaways
ABC assigns overhead through activities: identify activities, pool their costs, choose a driver for each pool, compute activity rates, and charge products by their use of each driver. Activities fall into unit, batch, product and facility levels, and only unit-level costs vary with volume. Low-volume, complex products often absorb far more batch- and product-level cost than a volume-based rate shows. Total overhead is unchanged; its distribution is more realistic. Facility costs are often left unassigned for decisions. ABC works in service businesses too.
Flashcards
Flashcard
Assigns overhead through the activities products use
Test your understanding
Question 1 of 5
A setup pool costs $180,000 and the plant expects 120 setups. A product needs 30 setups. How much setup cost is assigned to it?
Question 2 of 5
Which cost is a batch-level cost?
Question 3 of 5
A product is assigned $96,000 of overhead under ABC and 8,000 units are made. Materials are $14 and labour $9 per unit. What is its full unit cost?
Question 4 of 5
A company switches from one labour-hour rate to ABC. What happens to its total manufacturing overhead?
Question 5 of 5
Under a single labour-hour rate, which product is most likely to be undercosted?